Excavation & subgrade
Strip topsoil. Cut to depth (typically 8 inches for a residential driveway). Compact subgrade in lifts with a plate compactor — this is the step that decides whether the pour lasts.
Stage 1 of 42
Form, base, and reinforcement
Form boards staked and leveled. 4 inches of compacted 3/4-inch clean stone base. Rebar or mesh placed on chairs so reinforcement actually sits inside the slab, not on the dirt.
Stage 2 of 43
Pour, screed, and finish
Concrete placed, screeded, bull-floated. We hand-edge, broom-finish (or stamp / expose), and saw-cut control joints at proper spacing — typically every 8–10 feet for a residential slab.
Stage 3 of 44
Cure and seal
Cure compound the same day. Stay off it for 24 hours, light traffic at 72, full load at 28 days. Optional densifier sealer in week two locks out road salt.
Stage 4 of 4